
Current Status
MVCA has completed an environmental assessment (EA) of the Kashwakamak Lake Dam located in the Township of North Frontenac on the main stem of the Mississippi River. An EA Project File Report (PFR), has been prepared in accordance with the Conservation Ontario’s Class Environmental Assessment for Remedial Flood and Erosion Control Projects and is being placed on public record for a 30-day review period from November 14th to December 16th, 2024. Written comments may be provided to the Project Team by December 16th, 2024, from the date of the public notice.
Project Background
The Environmental Assessment phase of this project is completed and MVCA is now moving into preliminary and detailed design. In preparation for that work, MVCA is undertaking site surveys and preparing terms of reference to issue this winter to secure engineering services. Currently, the design phase is anticipated to be completed by the end of 2025, with construction to commence in 2026. This site will be updated if timelines change. In the meantime, MVCA will liaise with adjacent property owners and the lake association to discuss design and construction details as needed.
Environmental Assessment Process
This project is being carried out in accordance with the process for Conservation Ontario’s Class EA for Remedial Flood and Erosion Control Projects under the Environmental Assessment Act. A Class EA characterizes the study area, identifies alternative solutions, evaluates each alternative’s potential impacts on the natural, cultural, social and economic environments, and identifies measures to mitigate potential adverse effects. The EA process ensures that community members, Indigenous communities, stakeholders, and public agencies are engaged at key points during the study to identify and consider options for resolving the issue.
Project Status
The project officially launched in May 2023 with a Notice of Intent for the Kashwakamak Lake Dam Class EA issued to stakeholders, the public, property owners, technical agencies, municipalities, and Indigenous Communities. Since then, several studies have been completed to support development and assessment of alternative approaches:
- Cultural Heritage Evaluation
- Existing Environmental Conditions Investigation
- Hydraulic Analysis Memorandum
- Marine Archaeological Assessment
- Stage 1 & 2 and Stage 3 Archaeological Assessments
- Draft Geotechnical Investigation and Design Recommendations
The Stage 2 Archaeological Assessment was completed in May 2024 during which a small Indigenous site was encountered. This prompted a Stage 3 Archaeological Assessment, which was completed in August 2024. The Stage 3 Assessment identified an assemblage of artifacts, including chipped stone and small mammal bones. Stage 4 mitigation options were investigated and an “avoid and protect” approach confirmed as the preferred option with input and acceptance from First Nations communities.
The team identified and evaluated five alternative approaches:
- Alternative 1: Do Nothing
- Alternative 2: Decommission the Existing Dam and Construct Passive Control System
- Alternative 3: Rehabilitation of the Existing dam
- Alternative 4: Replace Existing Dam at the Same Location
- Alternative 5: Construct New Dam Downstream
The technically preferred option is Alternative 4: Replace Existing Dam at the Same Location.
An EA Project File Report (PFR), was prepared in accordance with the Conservation Ontario’s Class Environmental Assessment for Remedial Flood and Erosion Control Projects that documents the above process, findings, and recommendation. Notices were published and the document was placed on public record for a 30-day review period from November 14th to December 16th, 2024. No objections were received by the deadline and the environmental assessment phase of this project is now considered complete.
Public Consultation
A Community Liaison Committee (CLC) was established in 2023 to hear various perspectives and obtain input at key points in the study process in advance of engaging the broader public through more traditional consultation means. CLC meetings were held in February and July 2024 and were attended by local residents and representatives from a local First Nation and the Kashwakamak Lake Association. The project team also organized a virtual Public Information Centre (PIC) in May 2024 to provide information to the public about the project and the recommended technically preferred alternative (Alternative 4). A recording of the PIC can be accessed here.