COVID-19 Update:

Our Administrative Office remains closed to the public due to COVID-19, but we are still open to serve you remotely. Please note that the Planning & Regulations department is receiving a higher than normal volume of planning applications and is working as quickly as possible to respond to all of them.

Your partner in risk management, resource conservation and stewardship

Shabomeka Dam Rehabilitation & Tender

Home > Current Initiatives > Shabomeka Dam Rehabilitation & Tender

Background

The Shabomeka Lake Dam has been the subject of several geotechnical and structural reports since the last rehabilitation in 1989. In 2019, a Class EA was completed that recommended reconstructing the concrete control structure and rehabilitating the two adjacent earth embankments.


Project

The site must be dewatered before work can begin. The concrete control structure will be demolished and rebuilt with an electrical bascule gate. A soil-cement-bentonite cut-off wall will be installed in the existing earth embankments. In addition, the north embankment will have an emergency overflow channel installed. At the end of the work, all soils will be stabilized, and the site will be restored to its original condition.

An early drawdown of the lake is required before work can begin. The drawdown timeline will be optimized to minimize recreational and ecological impacts while meeting the requirements for construction. It's critical to the success of the project that the lake is at its minimum target by mid- to late- September.

The drawdown will begin the week of August 30th, 2021. The lake will drop 5-10 cm per day before reaching a minimum of 269.30 MASL by September 20, 2021. The tentative project schedule is provided below:

DatesProposed WorksTarget Levels
July 26th – Aug. 30th  Site clearing, water levels gauge removed.271.10 – 270.90
Aug. 30th – Sept. 6thDrawdown begins.  The lake will drop 5-10 cm per day.270.90 – 270.20
Sept. 7th – Sept. 14thDrawdown continues.270.40 – 269.50
Sept. 15th – 22ndDrawdown finishes.  Access to the structure is restricted. 269.90 – 269.30
Sept. 22nd – 30thStaging area set up, cofferdam and access road are installed.
Demolition of existing control structure.
269.40 – 269.30
Oct. 1st – 31stExcavation of SCB trenches, construction of the new control structure.
Embankment crest heightening, placement of rip rap on the upstream face. 
269.40 – 269.30
Nov. 1st – 30th  Installation of the bascule gate.269.40 – 269.30
Dec. 1st - Jan. 15thTesting and commissioning of new structure.269.40 – 269.30

Access to the north shore will be provided downstream of the worksite for the duration of the project.  By completing the work in the fall, we will be able to return to seasonal water levels in the spring. 

The new structure will help mitigate extreme water conditions and protect the lake in a changing climate.  The inconvenience of an early drawdown will pay dividends to all stakeholders for many years into the future.

Thank you for your patience and support as we complete this important project!


In August 2021, the project was tendered for construction. The tender results are provided below:

Tender Opening - SHABOMEKA LAKE DAM REHABILITATION (MVCA CONTRACT NO. 2021-02)

TENDER DATE OPENING: SEPTEMBER 1, 2021

SUBMISSION COMPANY
Louis W. Bray Construction Limited
GDB Constructeurs
Canadyne Navigation


PROJECT CONTACTS:

Juraj Cunderlik, Ph.D., P.Eng.
Director, Water Resources Engineering
jcunderlik@mvc.on.ca
Christopher McGuire, P.Eng.
Water Resources Engineer
cmcguire@mvc.on.ca