COVID-19 Update:

Our Administrative Office remains closed to the public due to COVID-19, but we are still open to serve you remotely. Please note that the Planning & Regulations department is receiving a higher than normal volume of planning applications and is working as quickly as possible to respond to all of them.

Your partner in risk management, resource conservation and stewardship

Shabomeka Lake Dam Rehabilitation

Home > Current Initiatives > Shabomeka Lake Dam Rehabilitation

Background

The Shabomeka Lake Dam has been the subject of several geotechnical and structural reports since the last rehabilitation in 1989. In 2019, a Class EA was completed that recommended reconstructing the concrete control structure and rehabilitating the two adjacent earth embankments.

Phase 1

Due to scheduling and material limitations, the MVCA will be adopting a phased construction approach for this project. The first phase will correct the highest risk deficiencies, as identified in past studies. The earth embankments will be rehabilitated through the installation of a soil-cement-bentonite cut-off wall, riprap protection and crest heightening. In addition, the north embankment will have an emergency overflow spillway installed. At the end of the work, all soils will be stabilized, and the site will be restored to its original condition. By completing the work in the fall, we will be able to return to seasonal water levels in the spring. 

Access to the north shore will be provided downstream of the worksite for the duration of the project. 

Tender Results

In September 2021, the updated project was tendered for construction. The tender results are provided below:

MVCA CONTRACT NO. 2021-03 - October 1, 2021

SUBMISSION COMPANY
Crains' Construction Limited
GDB Constructeurs
Louis W. Bray Construction Limited

The contract has been awarded to Louis W. Bray Construction Limited and construction is expected to start the week of November 15, 2021.

Project Schedule

DatesProposed WorksTarget Levels
OctoberDrawdown continues.  269.80 – 269.20
NovemberStaging area and access road are installed.269.40 – 269.20
DecemberExcavation of SCB trenches, embankment crest heightening, placement of rip rap on the upstream face. 269.40 – 269.20
JanuaryInspections and site cleanup.269.40 – 269.20

The rehabilitated earth embankments will increase the resiliency during extreme water conditions and protect the lake in a changing climate.  The associated inconveniences will pay dividends to all stakeholders for many years into the future.

Thank you for your patience and support as we complete this important project!

Project Contacts

Juraj Cunderlik, Ph.D., P.Eng.
Director, Water Resources Engineering
jcunderlik@mvc.on.ca
Christopher McGuire, P.Eng.
Water Resources Engineer
cmcguire@mvc.on.ca